AGILE PROJECT MANAGEMENT TECHNIQUES AND PERFORMANCE OF ROAD CONSTRUCTION PROJECTS IN NAIROBI CITY COUNTY, KENYA

Authors

  • Chagusia Dennis Mavundi Jomo Kenyatta University of Agriculture and Technology image/svg+xml
  • Dr. Maurice Pedo Jomo Kenyatta University of Agriculture and Technology image/svg+xml

Abstract

Purpose of the study: The study examined the influence of iterative planning and review cycles, collaborative sprint planning, enhanced customer involvement and financial management on the performance of road construction projects in Nairobi City County, Kenya.

Statement of the problem: Road construction projects face persistent challenges involving delays, cost overruns and stakeholder dissatisfaction. Existing evidence provides limited understanding of the distinct contributions of agile management techniques when examined together within major urban road projects.

Research methodology: A quantitative descriptive cross-sectional design was adopted. The target population comprised 171 stakeholders associated with the Nairobi Eastern and Western Bypass projects. A sample of 120 respondents was selected through stakeholder stratification and snowball recruitment. All questionnaires were returned, and 115 complete cases were available for multiple regression. Structured questionnaire data were analysed using descriptive statistics, Pearson correlation and multiple linear regression in SPSS version 28.

Findings: The four techniques jointly explained 71.3% of the variation in perceived project performance (R² = .713; adjusted R² = .703; F(4, 110) = 68.450, p < .001). Collaborative sprint planning (B = .212, β = .221, p = .009), enhanced customer involvement (B = .344, β = .365, p < .001) and financial management (B = .223, β = .262, p = .001) had positive, statistically significant adjusted associations with performance. Iterative planning and review cycles had a positive but statistically insignificant adjusted association (B = .136, β = .117, p = .210).

Conclusion: Collaborative planning, customer involvement and financial management were significant correlates of performance within the combined model. Customer involvement had the largest standardised coefficient, while iterative planning did not explain a statistically significant additional contribution after adjustment for the other techniques.

Recommendations: Project teams should strengthen joint work planning, institutionalise community feedback and improve accessible financial reporting. Review meetings should produce assigned corrective actions and inform subsequent work plans. These recommendations should be applied with attention to the study's two-project scope and reliance on stakeholder perceptions.

Keywords: Agile project management, iterative planning, collaborative sprint planning, customer involvement, financial management, road construction, Nairobi City County.

Author Biographies

  • Chagusia Dennis Mavundi, Jomo Kenyatta University of Agriculture and Technology

    Jomo Kenyatta University of Agriculture and Technology, Kenya

  • Dr. Maurice Pedo, Jomo Kenyatta University of Agriculture and Technology

    Jomo Kenyatta University of Agriculture and Technology, Kenya

References

Aziz, Z. A. (2021). The influence of communication on project success: A survey of the SANRAL Gauteng e-tolling project in South Africa. Communicare: Journal for Communication Studies in Africa, 40(2), 101–128. https://doi.org/10.36615/jcssa.v40i2.1313

Badran, S. S., & Abdallah, A. B. (2025). Lean vs agile project management in construction: Impacts on project performance outcomes. Engineering, Construction and Architectural Management, 32(5), 2844–2869. https://doi.org/10.1108/ECAM-05-2023-0470

Beck, K., Beedle, M., van Bennekum, A., Cockburn, A., Cunningham, W., Fowler, M., Grenning, J., Highsmith, J., Hunt, A., Jeffries, R., Kern, J., Marick, B., Martin, R. C., Mellor, S., Schwaber, K., Sutherland, J., & Thomas, D. (2001). Manifesto for agile software development. https://agilemanifesto.org/

Carver, C. S., & Scheier, M. F. (1982). Control theory: A useful conceptual framework for personality–social, clinical, and health psychology. Psychological Bulletin, 92(1), 111–135. https://doi.org/10.1037/0033-2909.92.1.111

Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014). Can agile project management be adopted by industries other than software development? Project Management Journal, 45(3), 21–34. https://doi.org/10.1002/pmj.21410

Connelly, L. M. (2008). Pilot studies. MEDSURG Nursing, 17(6), 411–412.

Donaldson, T., & Preston, L. E. (1995). The stakeholder theory of the corporation: Concepts, evidence, and implications. Academy of Management Review, 20(1), 65–91. https://doi.org/10.5465/amr.1995.9503271992

Freeman, R. E. (1984). Strategic management: A stakeholder approach. Pitman.

Gemino, A., Reich, B. H., & Serrador, P. M. (2021). Agile, traditional, and hybrid approaches to project success: Is hybrid a poor second choice? Project Management Journal, 52(2), 161–175. https://doi.org/10.1177/8756972820973082

Highsmith, J. (2009). Agile project management: Creating innovative products (2nd ed.). Addison-Wesley.

Hoda, R., Salleh, N., & Grundy, J. (2018). The rise and evolution of agile software development. IEEE Software, 35(5), 58–63. https://doi.org/10.1109/MS.2018.290111318

Layton, M. C., Ostermiller, S. J., & Kynaston, D. J. (2020). Agile project management for dummies (3rd ed.). Wiley.

Mitchell, R. K., Agle, B. R., & Wood, D. J. (1997). Toward a theory of stakeholder identification and salience: Defining the principle of who and what really counts. Academy of Management Review, 22(4), 853–886. https://doi.org/10.5465/amr.1997.9711022105

Muvawala, J., Sebukeera, H., & Ssebulime, K. (2021). Socio-economic impacts of transport infrastructure investment in Uganda: Insight from frontloading expenditure on Uganda's urban roads and highways. Research in Transportation Economics, 88, Article 100971. https://doi.org/10.1016/j.retrec.2020.100971

Oppong, G. D., Chan, A. P. C., & Dansoh, A. (2017). A review of stakeholder management performance attributes in construction projects. International Journal of Project Management, 35(6), 1037–1051. https://doi.org/10.1016/j.ijproman.2017.04.015

Ouchi, W. G. (1979). A conceptual framework for the design of organizational control mechanisms. Management Science, 25(9), 833–848. https://doi.org/10.1287/mnsc.25.9.833

Russo, D. (2021). The Agile Success Model: A mixed-methods study of a large-scale agile transformation. ACM Transactions on Software Engineering and Methodology, 30(4), Article 52. https://doi.org/10.1145/3464938

Schwaber, K., & Sutherland, J. (2020). The Scrum guide: The definitive guide to Scrum: The rules of the game. https://scrumguides.org/scrum-guide.html

Seboru, M. A. (2015). An investigation into factors causing delays in road construction projects in Kenya. American Journal of Civil Engineering, 3(3), 51–63. https://doi.org/10.11648/j.ajce.20150303.11

Sergeeva, N. (2020). Towards more flexible approach to governance to allow innovation: The case of UK infrastructure. International Journal of Managing Projects in Business, 13(1), 1–19. https://doi.org/10.1108/IJMPB-10-2018-0216

Serrador, P., & Pinto, J. K. (2015). Does Agile work? A quantitative analysis of agile project success. International Journal of Project Management, 33(5), 1040–1051. https://doi.org/10.1016/j.ijproman.2015.01.006

Sinha, A. K., & Jha, K. N. (2021). Financing constraints of public–private partnership projects in India. Engineering, Construction and Architectural Management, 28(1), 246–269. https://doi.org/10.1108/ECAM-06-2018-0237

Wiener, N. (1961). Cybernetics: Or control and communication in the animal and the machine (2nd ed.). MIT Press.

Yamane, T. (1967). Statistics: An introductory analysis (2nd ed.). Harper & Row.

Downloads

Published

2026-11-17

Issue

Section

Articles

How to Cite

Mavundi, C. D., & Pedo, M. (2026). AGILE PROJECT MANAGEMENT TECHNIQUES AND PERFORMANCE OF ROAD CONSTRUCTION PROJECTS IN NAIROBI CITY COUNTY, KENYA. African Journal of Emerging Issues, 8(35), 58-82. https://ajoeijournal.org/sys/index.php/ajoei/article/view/1374

Article metrics

Views: 32 Downloads: 17

Day by day
  • Views
  • Downloads
20 10 0 17 Nov 18 Nov 19 Nov
View as table
Date Views Downloads
17 November 20261911
18 November 202693
19 November 202643